Zoning regulations

The zoning regulations

The regulations will turn the Energy Act 2023's zoning powers into working rules. Until they are in force, no zone can be designated and no building can be required to connect.
PendingNot yet laid before Parliament

The January 2026 government response expected the regulations to be laid in spring 2026, subject to parliamentary time. At our last check nothing had been laid: no draft or made zoning regulations appear on legislation.gov.uk or Parliament's statutory instruments tracker, and in October 2026 the energy minister still described them as yet to go live.

Checked 8 November 2026. Source: The role of heat networks in the energy transition (GOV.UK speech by the energy minister, 22 Oct 2026)

Timetable

How the policy got here

ItemPositionStatus
First zoning consultationRan from 8 October to 19 November 2021; government response published 16 June 20228 October 2021 · Proposals for heat network zoning, 2021 consultation (GOV.UK)In force
Legal powers for heat network zonesEnergy Act 2023, Part 8, Chapter 2 (sections 226 to 237)The Act gives the government powers to create heat network zones in England. It became law on 26 October 2023, but zoning cannot work until regulations are made under it.26 October 2023 · Energy Act 2023, Part 8, Chapter 2: heat network zones (legislation.gov.uk)In force
Second zoning consultationPublished 18 December 2023, closed 26 February 202418 December 2023 · Proposals for heat network zoning 2023 (GOV.UK consultation)In force
Government response on zoningPublished 21 January 2026Sets out the policy design: which buildings must connect, exemptions, penalties and the roles of each body.21 January 2026 · Proposals for heat network zoning: government response (DESNZ, Jan 2026)Announced
Heat network zoning regulationsNot yet laid before ParliamentThe January 2026 government response expected the regulations to be laid in spring 2026, subject to parliamentary time. At our last check nothing had been laid: no draft or made zoning regulations appear on legislation.gov.uk or Parliament's statutory instruments tracker, and in October 2026 the energy minister still described them as yet to go live.Expected 2026–27 · The role of heat networks in the energy transition (GOV.UK speech by the energy minister, 22 Oct 2026)Pending

Policy, pending

Which buildings could be required to connect

These are the categories in the January 2026 government response. They become law only when the regulations are made, and could still change.
ItemPositionStatus
New buildingsNew buildings that receive planning permission after the zone is designatedProposals for heat network zoning: government response (DESNZ, Jan 2026)Pending
Buildings with communal heatingExisting buildings with communal heating, both domestic and non-domesticProposals for heat network zoning: government response (DESNZ, Jan 2026)Pending
Large existing non-domestic buildingsExisting non-domestic buildings with a wet heating system and average heat demand above 100 MWh a yearWhere metered data is missing, demand will be estimated using energy-density benchmarks for the building's use type.Proposals for heat network zoning: government response (DESNZ, Jan 2026)Pending
When a building can be required to connectOnly when the zone developer asks for it and the zone coordination body is confident the building can be connected in timeProposals for heat network zoning: government response (DESNZ, Jan 2026)Pending
Individual homesExisting individually heated homes are not required to connectProposals for heat network zoning: government response (DESNZ, Jan 2026)Pending
Crown buildingsNot covered: zoning law does not apply to bodies with Crown statusThe government says it is exploring legislative changes that could bring Crown bodies in later.Proposals for heat network zoning: government response (DESNZ, Jan 2026)Pending
Campus energy centresGovernment intends to extend the requirement to buildings containing an energy centre that supplies a campus networkProposals for heat network zoning: government response (DESNZ, Jan 2026)Pending

Policy, pending

The notice process

ItemPositionStatus
Issuing a connection noticeThe zone coordination body issues the notice within 2 weeks of the zone developer's requestProposals for heat network zoning: government response (DESNZ, Jan 2026)Pending
Agreement phaseAt least 6 months from receiving the noticeIn this time you either agree a connection date with the zone developer or apply for a temporary exemption.Proposals for heat network zoning: government response (DESNZ, Jan 2026)Pending
Connection windowAt least 12 months longThe window can run at the same time as the 6-month agreement phase.Proposals for heat network zoning: government response (DESNZ, Jan 2026)Pending
Temporary exemptionsUp to 2 years from the end of the proposed connection windowProposals for heat network zoning: government response (DESNZ, Jan 2026)Pending
Paying for connectionWhen zoning launches, a building required to connect cannot be made to pay a connection fee; connection costs will be negotiated commerciallyGovernment found that the Energy Act 2023 does not give developers power to charge a connection fee to buildings required to connect, and intends to fix this through new primary legislation. Until then it expects few connection notices to be issued. Planned caps once the law changes: no up-front charge for domestic buildings with existing communal heating, the up-front cost of a building-scale heat pump for new buildings, and a level still to be confirmed for non-domestic buildings.Proposals for heat network zoning: government response (DESNZ, Jan 2026)Pending

Policy, pending

Grounds for exemption

ItemPositionStatus
Exemption: existing low-carbon heatingExisting low-carbon heating with an expected lifespan of more than 2 yearsProposals for heat network zoning: government response (DESNZ, Jan 2026)Pending
Exemption: legal or contractual barriersLegal or contractual requirements that prevent connection, such as restrictive covenants or lease termsProposals for heat network zoning: government response (DESNZ, Jan 2026)Pending
Exemption: building safety remediationFire-safety cladding or other building safety remediation worksProposals for heat network zoning: government response (DESNZ, Jan 2026)Pending
Exemption: permanent physical barriersPermanent physical features, such as the structure or ground conditions, that make connection impossibleProposals for heat network zoning: government response (DESNZ, Jan 2026)Pending
Exemption: technical incompatibilityEnduring technical incompatibility that cannot be fixed without significant cost, such as direct electric heatingProposals for heat network zoning: government response (DESNZ, Jan 2026)Pending
Exemption: conservationConservation requirements, such as listed status, where connection is impossible or disproportionately costlyProposals for heat network zoning: government response (DESNZ, Jan 2026)Pending

Policy, pending

Penalties

ItemPositionStatus
Maximum penaltyUp to £1 million or 10% of annual turnover, whichever is higherThis is proposed policy. Fixed penalties are also planned. The figures are not yet in regulations.Proposals for heat network zoning: government response (DESNZ, Jan 2026)Pending
Appeals against penaltiesAppeals to be lodged within 28 daysProposals for heat network zoning: government response (DESNZ, Jan 2026)Pending

Policy, pending

Who does what

ItemPositionStatus
Heat Network Zoning AuthoritySits within DESNZ at first, then moves to the Warm Homes Agency once that is set upProposals for heat network zoning: government response (DESNZ, Jan 2026)Pending
Zone coordination bodiesSet up by local government; the zoning authority can step in if councils cannot agree within 28 daysProposals for heat network zoning: government response (DESNZ, Jan 2026)Pending
Zone developersAppointed through competition, with exclusive rights to develop a heat network in the zone delivery areaProposals for heat network zoning: government response (DESNZ, Jan 2026)Pending
Zone developer design stageEstimated to last 12 to 18 months once a single zone developer is selectedAfter this stage the developer must give the zone coordination body a pricing schedule for consumers in the zone.Heat network zoning consultation 2023: summary of government response (GOV.UK, Jan 2026)Pending

Explainer: the Authority, coordinators and developers

Designation

Zones designated so far

ItemPositionStatus
Heat network zones designatedNone yetNo zone can be formally designated until the zoning regulations are in force.After regulations · The role of heat networks in the energy transition (GOV.UK speech by the energy minister, 22 Oct 2026)Not yet
Support after the regulations go liveAt least 10 of the biggest English towns and cities to get government support to set up zones soon after the zoning regulations go live22 October 2026 · The role of heat networks in the energy transition (GOV.UK speech by the energy minister, 22 Oct 2026)Announced
Call for zone opportunity areasLocal authorities invited to submit zone opportunity areas by 29 May 202630 March 2026 · Heat Networks Delivery Unit (GOV.UK)Announced

See every place and its stage

Elsewhere

Scotland and Wales

These regulations will apply in England only. Scotland has its own zoning law under the Heat Networks (Scotland) Act 2021, and Wales has no zoning regime. How the three compare.