Coventry heat network zone
Last change
UnreviewedThis record was compiled from the sources below and has not yet had an editor’s final check. Report an error.
Summary
Where Coventry has got to
Coventry has run its Heatline network, fed by heat from the city's energy-from-waste plant, for more than a decade. A November 2025 council briefing set out proposals to extend the operating concession to 2043. The February 2025 report centres the main zone on everything inside the ring road.
Status
Stage history
- 1Pilot
Listed among the 28 places in the government's heat network zoning pilot, which published its first outputs in September 2024.
Source: Heat networks zoning pilot (GOV.UK)
Geography
Zone boundaries and candidate areas
The strategic zones are the City Centre, covering everything inside the ring road, Walsgrave, Torrington Avenue and the University of Warwick.
Source: Heat network zone opportunity report: Coventry (by Arcadis)Candidate areas come from government-commissioned studies and council work. They are not legal boundaries. A zone’s boundary is fixed only when it is designated under the zoning regulations.
Delivery
Developers and partners
We have found no appointed or bidding developer for Coventry.
No statutory zone developer can be appointed until a zone is designated. Partners appointed by councils before then are listed as development or delivery partners.
Today
Existing heat networks
Heatline · Coventry District Energy Company
Source: Heatline District Heating Update (Coventry City Council, Nov 2025)University of Warwick campus network · University of Warwick
Source: Heat network zone opportunity report: Coventry (by Arcadis)
Paper trail
Council and government documents
| Date | Document |
|---|---|
| Heatline District Heating Update (scrutiny briefing)Coventry City Council | |
| Heat network zone opportunity report: Coventry (by Arcadis)Department for Energy Security and Net Zero |
Changelog
Changes logged for Coventry
Alerts
Get an email when Coventry changes stage
Sources
Sources for this page
- Heat networks zoning pilot (updated 25 November 2025) — Department for Energy Security and Net Zero, 25 November 2025
- Heat network zone opportunity report: Coventry (by Arcadis) — Department for Energy Security and Net Zero, 14 February 2025
Record last checked .